Floor levelcrete is done.

Wed, 2 July

Concreting on floor arrangement in studio rooms are done. In back rooms the 1st level of roof is poured.
On the 2nd level balcony and barricade over the check room are assembled.
We start laying of pediment, technology is still the same – we pour sand into concrete bricks hollows.
We checked the condition of village electricity.
Condition is depressed.
One transformer of 50kVt is for 50 houses.
The transformer was produced in 1966.
No wonder that in rush-hours voltage is 140В below.
Fortunately, high-voltage line of 10kV is just by studio.
We are preparing expert’s report and going to attach to it our own transformer, in that way, all problems concerning studio power supply will take away.

Photo: Sergiy Dedishchev.
Comments:


View: North- South.



View: North- South.


Balcony


View: West - East


Balcony


View: West - East


On the 2nd level, view from the balcony


Floor over the check room.


Floor over the check room.


2nd level - common view


Cap and interior foundation in studio rooms


Cap and interior foundation in studio rooms


Cap in studio rooms


Long-suffering transformer


Long-suffering transformer


Long-suffering transformer


Long-suffering transformer


Long-suffering transformer

 

designed by art
© 2008 Spivaki Records